Construction Project Updates

We’re excited about our First Impressions 2018 Terminal Upgrade. We believe this project will offer our customers the finest airport experience in Wisconsin. When complete, our travelers will enjoy a new landside restaurant overlooking an active ramp, expanded TSA checkpoint with three lanes, mother’s room, conference room, and brand new gift shop, as well as a fresh updated look throughout the entire airport lobby. We are grateful for the support of our community and look forward to providing our customers with the best possible travel experience.

Abe Weber, Airport Director

Upgrades to ticket counter and lobbyUpgrades to ticket counter and lobby
Spacious new lobbySpacious new lobby

List updated weekly. All dates subject to change.

Sept 17 - Oct 11

Work

Construction and updating of new TSA checkpoint lanes.

Impact

No impact to travelers. Current 2 TSA lanes (including TSA PreCheck lane) will remain open throughout project.

Customers may hear construction  noise at times.

TSA checkpoint area being updated to provide a more comfortable and convenient customer experience.

 

Sept 17 - Oct 31

Work

Temporary wall put up around business center past TSA checkpoint.

Impact

Business Center closed for duration of project and will re-open Fall 2018.

Customers may hear construction noise at times.

 

 

Sept 17 - Dec 28

Work

Temporary wall put up around baggage claim carousel 1.

Impact

Carousel 1 closed. Luggage will arrive via Carousel 2.

Sept 17 - Dec 28

Temporary wall put up around business area across from Gift Shop.

No impact to customers. Follow temporary signage to baggage claim.